Kitchen timelines

How long does a kitchen renovation take in Dubai?

Weeks on site, days in approvals, and hours a day set by your community's rulebook. What decides each part, what stretches it, and how to keep cooking while the work goes on.

The timeline

Kitchen renovation timeline: approvals first, then the build

How long does a kitchen renovation take? Longer than the fitting, because the clock starts with paperwork and the working day is shorter than it looks. A Dubai kitchen passes through three stages that each set their own pace: the approvals before anyone arrives, the weeks of work on site, and the checks that close the job. The figures below are the ones developers, authorities and one UAE contractor publish, read in September 2026.

How long does a kitchen renovation take in Dubai?

Plan on about a month on site for a kitchen that keeps its layout, plus the approvals before it. First Unicorn Interiors publishes 3 to 4 weeks for its budget kitchen at AED 35,000 to 55,000, the only kitchen programme printed by the companies on our price page. Before day one, a Dubai Holding community wants the request 24 hours ahead on its app, Emaar decides an NOC within 3 business days, and Town Square takes 2 working days for new cabinets and 5 for new counters. Moving the sink, the gas or a wall adds a Municipality or Trakhees permit on top.

Every stage, with its published time

Kitchen renovation stages in Dubai and the times their publishers state, read September 2026
StageWhat it coversPublished timePublished by
Community requestDubai Holding communities, by app or by emailAt least 24 hours ahead by app, 72 by emailDubai Holding Community Management
Developer NOCEmaar minor or major works3 business days from complete documentsEmaar Community Management
Community approvalTown Square: new cabinets, or new counters2 working days minor, 5 majorTown Square homeowner manual
Notice of worksTilal Al Ghaf, with the contractors named48 hours before work startsTilal Al Ghaf Community Rules
Authority permitMunicipality modification, if the drawings change3 working days statedDubai Municipality, service 4127
Extra powerDEWA building NOC, then design approval up to 150 kW2 working days, then 1DEWA
Work on siteBudget kitchen, layout kept3 to 4 weeksFirst Unicorn Interiors
Permit validityDubai Holding Minor Modifications Permit7 days at most; extensions in writingDubai Holding Community Management
Close-outDubai Holding inspection after the completion noticeAbout 21 days; 30 days to put rightDubai Holding Community Management
Close-out on Trakhees landModification Completion Certificate3 working days targetedTrakhees
Kitchen renovation stages in Dubai and the times their publishers state, read September 2026

Two rows deserve a second look. A Minor Modifications Permit is valid for 7 days at most, while the one published kitchen programme runs 3 to 4 weeks, so in a Dubai Holding community ask for the extension in writing before the permit runs out. And Dubai Holding wants approved works finished within six months, sooner if the government approval expires first, which matters when cabinets are made to order.

An empty room undergoing renovation with exposed plumbing and electrical conduits installed on unfinished walls

How long does a full kitchen refurb take?

On site, the one published figure is 3 to 4 weeks, for a budget kitchen that keeps its layout. Inside those weeks the order is fixed, and one step always waits on another: the worktop cannot be templated until the base cabinets are fixed and level, and it is then cut away from the house before it can be fitted. That gap in the middle is the part to ask each contractor about, in days, in writing.

  1. Strip-out: the old units, worktop and tiles come out, and water, power and gas are isolated.
  2. First fix: new water, drain and power runs, and any gas work by a licensed gas contractor.
  3. Walls and floor made good, and the ceiling too if the extraction route changes.
  4. Base units fixed and levelled; tall and wall units follow.
  5. Worktop templated from the fitted units, cut off site, then fitted.
  6. Second fix: sink, tap, hob, oven and dishwasher connected; splashback and lighting finished.
  7. Snagging, cleaning and the community's close-out, where it has one.

Which approvals set the start date?

Your developer's, and for a kitchen that keeps its layout that is often the only one. It is short: 3 business days at Emaar, and 2 or 5 working days in Town Square depending on the class of work. In the Nakheel villa communities, Dubai Holding's 2026 rulebook now governs, and it promises only a decision within a reasonable period of time. What has to be settled before that application, and in which order, is on our what comes first page.

A layout change adds an authority step after the developer's. Dubai Municipality states 3 working days for a modification permit, and DEWA 2 working days for the building NOC behind a request for more power. Our layout permit guide explains which moves trigger which step, and the hub lists the Emaar NOC documents that go in the file.

Ask for a programme in weeks

How many hours a day can the work run?

Fewer than a normal working day for the noisy parts. Demolition, drilling and stone cutting have to fit noisy-work windows that add up to five hours a day in an Emaar villa, 10 am to 1 pm plus 3 pm to 5 pm, and six in a Dubai Holding community, which opens at 9 am instead. Quieter work, assembly and connections, can run longer: Dubai Holding allows minor works from 8 am to 6 pm, Monday to Saturday. Neither rulebook allows noisy work on a Sunday or a public holiday.

Deliveries have windows of their own. Emaar's 2026 villa rules keep bulk deliveries to the morning, 10 am until 1 pm, from Monday to Saturday. Dubai Holding wants 48 hours' notice before large vehicles arrive and every load cleared the same day, and in Aldar towers in Abu Dhabi a lift booking lasts at most 2 hours. A cabinet delivery that misses its window waits for the next one.

Can you use your kitchen during the renovation?

For most of it, no. From strip-out to the second fix the sink has no drain, the hob has no supply and the room is a site, so plan to cook somewhere else for the weeks on site. A fridge moved to another room, a kettle and a plug-in induction plate cover breakfasts and simple dinners; a villa with an outdoor barbecue has an easier month.

The rulebooks protect your evenings. Dubai Holding does not let workers stay in the home beyond the permitted hours without the community manager's written approval, and Town Square's manual bars workers from staying overnight. What they cannot protect is the water: expect the supply to be isolated on strip-out day and again when the new sink is connected, and keep a bathroom basin free for the kitchen's jobs.

What makes a kitchen renovation take longer than planned?

  • Moving a service. A sink, gas point or extractor in a new place adds a trade and an authority step, and in some buildings a refusal.
  • The approval class. In Town Square, new counters are major works at 5 working days, where new cabinets alone are minor works at 2.
  • The worktop gap. Templating waits for fixed cabinets, and the top is cut off site, so a late cabinet delivery pushes the worktop with it.
  • A permit that runs out. Dubai Holding's Minor Modifications Permit lasts 7 days unless it is extended in writing.
  • Summer outdoors. The federal midday break, 12.30 pm to 3 pm from 15 June to 15 September, halts work in the open, so a top cut outside or a noon delivery moves to the morning.
  • A meter that moves. If the electricity meter has to be shifted, DEWA issues its Electricity Network Modification estimate within 10 working days.

Kitchen timelines in Abu Dhabi, Sharjah and Ajman

In Abu Dhabi the Maintenance Permit's service time is 7 working days in the capital and 5 in Al Ain or Al Dhafra, per the Department of Municipalities and Transport, and a Building Permit takes 10 once walls or spaces change; a contractor files the first and a consultant the second. Ajman states 2 days for its Maintenance Permit and 7 days to return the deposit paid on it. Sharjah publishes no service time for its residential maintenance permit. The routes are set out on our Abu Dhabi permits, Sharjah route and Ajman fees pages.

Whatever the emirate, a quote that states the programme in weeks, and the payments against finished stages, is the one to hold a contractor to. The hub's payment schedule guide shows how to tie the two together. Budgets begin at AED 12,000 for a small refit on MBC Renovation Services' list, with what kitchens cost set out band by band, and our kitchen quotes service puts one brief to several contractors so their programmes can be compared too.

Related questions

Kitchen timing questions

Can a kitchen be renovated during Ramadan?
Dubai Holding's 2026 rulebook sets no separate Ramadan hours, and Emaar publishes none either. Ask your community for its working hours in writing before you book a start date in that month.
How long does the worktop take after the cabinets go in?
It depends on the fabricator's queue, and none of the companies on our price page publishes it. The sequence never changes, template from the fitted base units, cut off site, then fit, so ask for the gap in days on the quote.
Do I need to move out during a kitchen renovation?
Rarely for a kitchen alone. Workers leave at the end of the permitted hours, and in Emaar and Dubai Holding communities noisy work also pauses from 1 pm to 3 pm. The disruption is the cooking, the dust and the water being off on the days the sink is disconnected.
Does moving the sink make the job longer?
Yes, in two ways. It adds a stage on site, because the new drain and supply go in before anything is fitted, and it can add a permit: relocation is not on Dubai Municipality's no-permit maintenance list, and in some buildings the developer refuses it.
When should the cabinets be ordered?
Once the layout and the approvals are settled, because the cabinets are made to the drawings and cannot follow a late change. Ask the supplier for the delivery date in writing and plan the strip-out around it, so the kitchen is not out of use while you wait.

Who you are dealing with

  • OperatorWebsiteOS LLC
  • Licence2646567.01
  • Cost to homeownerNone
  • Figures datedSeptember 2026

Tell us about the kitchen

Your community, the kitchen's size and when you would like to start. We come back with contractors who quote against the published bands and put the programme in writing, in weeks.