In Dubai, a decision and a signature before any hammer: whether the sink, hob and extractor stay put, and the approval that decision sets off. The order, step by step, with who does each one.
The order
What comes first in a kitchen renovation is a decision, not a demolition. In a Dubai home the first question is whether the sink, the hob and the extractor keep their present connections to water, drainage, gas and outside air, because that answer sets the approval, the trades and the programme that follow. Everything below runs in the order a job meets it.
What comes first in a kitchen renovation in Dubai?
The layout decision, then the approval it triggers, then the order for the units, and only then the strip-out. A kitchen that keeps its services usually needs the developer's consent and little else: 3 business days for an Emaar NOC once the file is complete, 2 working days in Town Square when only the cabinets change and 5 when the counters do. Moving a service can add a Municipality or Trakhees permit. Units are ordered once the drawings are approved, and water, power and gas are isolated before anything comes out. Our timeline guide turns the order into weeks.
| Step | What happens | Waits for | Who does it |
|---|---|---|---|
| 1. Decide the layout | Keep or move the sink, hob, extractor and any wall | Nothing: it comes first | You, with the designer or contractor |
| 2. Measure and draw | Wall lengths, service points, window and door positions | The layout decision | Designer or contractor |
| 3. Classify the work | Maintenance, décor or a modification, stated in writing | The drawing | Accredited contractor or registered consultant |
| 4. Developer consent | NOC or community permit, with the contractor named | A complete file | You apply; the community decides |
| 5. Authority and utility | Municipality or Trakhees permit if the drawings change; DEWA if the load rises | Developer consent, where the developer sets that order | Consultant, contractor or enrolled firm |
| 6. Order the units | Cabinets and appliances to the approved drawings | Approvals in hand | Contractor or supplier |
| 7. Isolate and strip out | Water, power and gas off; the old kitchen removed | A firm delivery date | Contractor; gas by a licensed gas contractor |
Steps 1 to 6 happen with the old kitchen still in use. That is the point of the order. Every week spent on decisions and paperwork before the strip-out is a week you are still cooking at home, and every week after it is not.
Send us the plan and the community

Because it decides which rules the job runs under. Dubai Municipality's no-permit maintenance list covers plumbing fittings, drainage and electrical work kept where they are; relocating them is not on it. Its décor circular frees décor works in units of up to 100 m² from any permit, and above 100 m² an accredited contractor self-permits online through Dubai BPS. Change the approved drawings and the job becomes a modification, filed by a registered consultant.
Developers draw the same line more sharply. Emaar's apartment factsheet rules out relocating MEP services, Town Square classes replacing the counters or adding a custom island as major works, and Dubai Holding wants an application before anything beyond maintenance and repair starts. Our kitchen design page covers the layout choices themselves.
It depends on the developer, and one of them writes it both ways.
Where a utility is involved it runs alongside: DEWA states 2 working days for the building NOC behind extra load and 1 working day for design approval up to 150 kW, filed by an enrolled consultant or contractor. The hub's guide to Dubai permits sets out each authority's route.
So the kitchen is out of use for the shortest time. Made-to-measure cabinets follow the approved drawings to the millimetre and cannot absorb a late change, so the order waits for the approval, and the strip-out then waits for a firm delivery date. Ask for the delivery date in writing before you agree a start date, because the strip-out is timed from it.
Book the delivery inside the community's window as well. Emaar's 2026 villa rules keep bulk deliveries and removals to mornings, 10 am to 1 pm, six days a week and never on a public holiday, and Dubai Holding asks for two days' warning before a large vehicle comes in.
Water, power and gas. The water is isolated at the valve for the kitchen or the flat, the power at the circuit that feeds the hob, oven and sockets, and the gas by a firm licensed to work on it. Dubai Municipality's contractor classification treats central gas distribution networks as an activity of their own, apart from building and décor contracting, so the cabinet fitter is often not the right firm to cap a gas line.
Ask the building management how the kitchen's gas is supplied before the strip-out is booked, because the answer decides who you call. On the Abu Dhabi plots Tasareeh reviews, its service card for the maintenance permit lists a signed contract with a waste transporter approved by Tadweer, so the old kitchen's removal is booked before the permit is.
A clean order before the start protects the weeks on site as well. Our Dubai rules page sets out each developer's approval, and our kitchen contractors quote against one brief that states the order.