Layout changes
Replacing units where they stand is maintenance. Moving the sink, the gas point or the extract duct is not. This page follows each move through the Municipality, your developer and the utility with a say in it.
Permits
There is no single kitchen layout change permit in Dubai. There are lines, drawn by Dubai Municipality, by your master developer and by DEWA, and a kitchen crosses one each time a service moves. Three moves do it: the sink with its water and drain, the hob with its gas or power, and the extractor with its duct to outside air. A fourth, taking out a wall, crosses all of them at once.
Do I need a permit to change my kitchen layout in Dubai?
Usually, and often from more than one body. Dubai Municipality's no-permit list covers maintaining a kitchen's plumbing, drainage and electrics where they already are; moving them is not on it. The move then runs either as décor work through an accredited contractor or, where it changes the approved drawings, as a modification permit filed by a registered consultant, and the contractor or consultant should state in writing which one applies. Your developer decides separately, and some say no outright: in an Emaar apartment, MEP services may not be relocated at all. The answer belongs in the kitchen design, before a unit is ordered.
| The move | Dubai Municipality | Developer's published rule | Who files |
|---|---|---|---|
| Sink and drain | Maintenance in place needs no permit; a new position is not maintenance | Emaar flats: MEP may not be moved. Town Square flats: floor tiles may not be lifted | Accredited contractor; a consultant if the drawings change |
| Hob and gas line | Gas pipework is a separately licensed contracting activity | Emaar's NOC covers Civil Defence rules where they apply | Licensed gas contractor; Civil Defence where required |
| Induction or bigger appliances | Electrical maintenance needs no permit; added load is DEWA's decision | None of these developers publishes one | An enrolled consultant or contractor, free to apply |
| Extractor and duct | No alteration may put a façade at risk | Emaar villas: no changes to elevations. Dubai Holding: façade work needs written approval | Consultant or contractor, after the developer |
| A wall comes out | Main structural elements: full review and laboratory testing | Emaar flats: no wall removal. Town Square: townhouses only, as major works | Registered consultant |
Read the table from right to left and a pattern shows: the homeowner files almost nothing. The developer's consent is requested by the owner; everything on the authority side is filed by an accredited contractor, a registered consultant or a firm enrolled with DEWA. The Municipality's own procedure sends the inspection of adjustments and décor work to its Building Control Department, and raises a Civil Defence task only where one is required.
Send us the old and new layout

Because a drain needs a fall, and the fall has to go somewhere. Waste runs to the building's drainage stack by gravity, so a sink moved away from its old position needs a new pipe sloping back to it, laid in the floor or hidden in a raised plinth. In a villa there is usually room for that. In a tower there often is not, and two developers close the question in writing.
Emaar's Home Modifications factsheet does not allow MEP services to be removed, relocated or covered in its apartments, nor existing floor tiles to be taken up, which rules out cutting a new drain run into the floor. Town Square's apartment manual says the same about tiles: they may not be removed or replaced, only overlaid, except on balconies. In those buildings, plan the new kitchen around the drain where it is, and put any change to the sink's position to the community in writing before it is drawn.
Villas have more room and a different rule set. Nakheel's 2023 villa codes listed plumbing maintenance, and a kitchen refit that leaves the wall layout alone, among the works needing no NOC; a new drain run is neither. In the same communities, Dubai Holding's 2026 rulebook requires an application first for any work other than maintenance and repair, so budget for one.
Not the kitchen fitter, unless it also holds a gas licence. Dubai Municipality's contractor classification lists central gas distribution networks as a contracting activity of its own, separate from building and décor contracting, which is why the firm that builds the cabinets and the firm that moves the gas pipe are often two companies. Before anything is drawn, ask the building's management how the kitchen is supplied and who maintains that supply, because the answer decides which firm you call.
Civil Defence sits above both. Dubai Civil Defence lists engineering services for authorised consultants, décor fit-out firms and LPG contracting firms; Civil Defence publishes no fee or timing for them, so the licensed gas contractor confirms both in the quote. Emaar builds the same layer into its sequence: the NOC first, then any Dubai Municipality, DDA or Civil Defence approval the work needs, then entry permits for the contractors.
Swapping gas for induction trades the gas question for an electrical one. Extra load is DEWA's decision, filed by an enrolled firm, with a building NOC in 2 working days and design approval in 1 working day for loads up to 150 kW.
Sometimes. A new duct outlet changes the outside of the building, and that is where the rules are tightest. Administrative Resolution No. (109) of 2022, the one that frees ordinary maintenance from permits, also says that architectural or structural alterations that may compromise the safety of a building or any of its façades may not be made. The developers go further.
Where the outside wall is closed to you, a recirculating hood needs no duct at all. It strips grease and smells and returns the air, steam included, to the room: an acceptable trade in a flat, a poor one over a hob in daily use.
Here the permit comes from Trakhees, not the Municipality. Nakheel's online services list a Request For Villa Alteration, and the order its design codes set out starts with the Nakheel NOC, followed by a Trakhees Modification Permit, a site-access NOC for the contractor and finally a gate pass. After the work, Trakhees issues a Modification Completion Certificate, which it targets at 3 working days, and under its own procedure a modified facility is not to be occupied before it is issued.
Nakheel's 2023 villa codes, withdrawn when Dubai Holding Community Management took over, set a fee for this application and a refundable deposit for the contractor; DHCM's 2026 rulebook confirms that fees exist but publishes no amount, deposit or turnaround, so ask for the figures when you apply. The layout decides whether you are in this chain at all, because under those codes a refit inside the existing walls needed only a gate pass. The hub's guide to Nakheel NOC types sets out every application.
Of the developer rulebooks on this page, Town Square's says the most about kitchen layouts, and it holds one contradiction worth knowing. New counters or a customised island are major works; so are false ceilings and breaking or opening any interior wall, which its manual allows in townhouses only. But the manual writes its approval order two ways: one clause puts the authority consents before the community's, another says to seek them only after Community Management approves the proposal. Ask Town Square, in writing, which order it applies to your job.
Emaar decides minor and major works within 3 business days of complete documents, for AED 1,000 or AED 2,000 in total, its AED 500 review fee included, and our Emaar application guide lists the documents it wants. Tilal Al Ghaf asks for the master developer's prior written consent to improvements, 48 hours' written notice with the contractors' details, and a work permit before anything starts, and it charges AED 5,000 plus AED 250 VAT to review alteration plans.
For the Municipality side of any of these, the hub's permit regimes guide separates maintenance, décor and modification, and our developer-by-developer rules take the Dubai communities one at a time. A kitchen that keeps its layout is priced from AED 12,000 in MBC Renovation Services' published list; one that moves services adds the approvals above and the trades behind them. When the plan is settled, our kitchen contractors price it from one brief.
The order
One plan showing where the sink, hob, fridge and extract sit today and where they will go, with any wall that moves.
The contractor or consultant states whether the job is maintenance, décor or a modification, and so who files what.
Emaar takes the owner's application first and the authority approvals after it; Dubai Holding wants evidence of the authority's consent inside the owner's application. Town Square's manual gives two orders, so ask which applies.
A Municipality or Trakhees permit where the drawings change, DEWA for extra load, and Civil Defence where gas work requires it.
A completion certificate where a permit was issued; on Trakhees land, the Modification Completion Certificate before the kitchen is used.